PROJECT RESULTS / Annual Technical Results

Year 3 : ESDRED TECHNICAL RESULTS to January 2007

Module 3 : Heavy Load Emplacement technology for Horizontal Disposal Concepts

Summary :

During the third year of the Project three (3) industrial scale heavy load emplacement machines, including test bench and related equipment, were fabricated and commissioned. At La Seyne-sur-Mer, France CNIM, on behalf of SKB and Posiva, designed and built the KBS-3H Demonstrator based on water cushion technology. Elsewhere, at Beaumont-Hague, Mécachimie designed and built Andra’s Spent Fuel (CU1) Emplacement Demonstrator and Bentonite Rings Emplacement Demonstrator both of which are based on using air cushion technology

Work completed :

Important Events Planned for 2007 :