PROJECT RESULTS / Annual Technical Results

Year 5 : ESDRED TECHNICAL RESULTS to January 2009

Module 1: Buffer Construction Technology for Horizontal Disposal Concepts

Summary :

In the 5th project year, the partners ONDRAF/NIRAS, EURIDICE, GRS and NDA and have finalized their remaining technical work within ESDRED. The partners ANDRA and NAGRA had already accomplished their technical scope in the preceding project year.

O/N and EURIDICE have executed the grout injection backfill test on the 30 m long full-scale mock-up. The technical feasibility of the injection technique was demonstrated, but the post-test evaluation also concluded that modifications to the grout composition will be necessary in future R&D (outside ESDRED), to achieve a sufficient setting rate after injection.

GRS has continued to run the performance tests on four seals of different clay/sand composition in boreholes in the Mont Terri URL. The results so far of these in situ tests, and also the results obtained from the preceding laboratory mock-up tests, confirm the advantageous sealing properties of moderately compacted clay/sand mixtures.

NDA has continued the non-intrusive monitoring development program based on in situ seismic tomography testing around the HG-A tunnel in the Mont Terri URL. The work undertaken confirms the general feasibility of high-resolution seismic measurements for monitoring waste repositories.

EURIDICE has completed the design of the steel support structure of the PRACLAY seal in the Mol URL. Further computer analyses and laboratory testing have improved the understanding of the interaction between the sealing material (MX-80) and the host rock.

Work completed:

Work in progress: Work within ESDRED has been completed

Important Events Planned for 2009:
(In direct association with the work performed within ESDRED)